9 Input Modeling
Input models provide the driving force for a simulation. In the simulation ofa queueing system, typica input models are the distributions of time between arrivals and of service times. For a supply-chain simulation, input models include the distributions of demand and of lead time. For the simulation of a reliability problem, the distribution of time to failure of a component is an example of an input model.
In real-world simulation applications, choosing appropriate distributions for input data is a major task from the standpoint of time and resource requirements. Regardless of the sophistication of the analyst, faulty models of the inputs will lead to outputs whose interpretation could give rise to misleading recommendations.
There are four steps in the development of a useful model of input data:
Collect data from the real system of interest. This often requires a substantial time and resource commitment. Unfortunately, in some situations it is not possible to collect data (for example, when time is extremely limited, when the input process does not yet exist, or when laws or rules prohibit the collection of data). When data are not available, expert opinion and knowledge of the process must be used to make educated guesses.
Identify a probability distribution to represent the input process. When data are available, this step typically begins with the development of a histogram of the data. Given the histogram and a structural knowledge of the process, a family of distributions is chosen. Fortunately,
several well-known distributions often provide good approximations in practice.
Choose parameters that determine a specific instance of the distribution family. When data are available, these parameters may be estimated from the data.
Evaluate the chosen distribution and the associated parameters for goodness of fit. Goodness of fit may be evaluated informally, via graphical methods, or formally, via statistical tests. The chi-square and the Kolmogorov–Smirnov tests are standard goodness-of-fit tests. If not satisfied that the chosen distribution is a good approximation of the data, then the analyst returns to the second step, chooses a different family of distributions, and repeats the procedure. If several iterations of this procedure fail to yield a fit between an assumed distributiona form and the collected data, the empirical form of the distribution may be used.
Each of these steps is discussed in this chapter. Although software is now widely available to accomplish Steps 2, 3, and 4—including such stand-alone programs as ExpertFit® and and such integrated programs as Arena’s Input Processor and @Risk’s BestFit®—it is still important to understand what the software does, so that it can be used appropriately. Unfortunately, software is not as readily available for input modeling when there is a relationship between two or more variables of interest or when no data are available. These two topics are discussed toward the end of the chapter.
1 Data Collection
Problems are found at the end of each chapter, as exercises for the reader, in textbooks about mathematics, physics, chemistry, and other technical subjects. Years and years of working these problems could give the reader the impression that data are readily available. Nothing could be further from the truth. Data collection is one of the biggest tasks in solving a real problem and it is one of the most important and difficult problems in simulation.
The focus of input modeling is on the statistical aspects of fitting probability distributions to data, distributions that will later provide the driving inputs to the simulation. However, before “fitting” can occur there needs to be accurate and relevant input data available (or collectible), and the properties o the data need to be well understood. Too often data are handed to input modeling software, which wil always fit some probability model to the data, whether it is justified or not. The following examples illustrate common pitfalls of this approach:
Example 1: Stale Data
A simulation study will investigate ways to reduce the time patients spend in a cancer screening clinic. One part of the screening protocol involves a nurse obtaining the patient’s history. In a 2002 study of nursing activities, observations of nurses taking patient histories were collected by a consulting firm. The hospital still has this data. Should it be used for input modeling in the current project?
In this case the answer is probably no, because deeper investigation by the engineers on the current project discovered that in 2008 the nurses stopped recording screening notes on a paper char and began entering them directly into a laptop computer. Therefore, the 2002 data are of a different history-taking process and may significantly misrepresent the current process. If current data canno
be collected, either due to the time required or the expense, then it would be better to use estimates provided by the nurses themselves rather than rely on the out-of-date study. Section 6 describes methods for converting expert opinion into probability distributions. The engineers might then check the nurses’ estimates by volunteering to have their own histories taken and timing the process to get a few actual data points.
Example 2: Unexpected Data
For security purposes people who enter a government building are required to pass through a security screening that includes a metal detector. Before new security protocols are implemented a simulation study will be conducted to assess their impact. To facilitate the study, 1000 observations of the time, in minutes, required to pass through the metal detector station were collected. The average value o these data was about 1/2 minute, with standard deviation almost the same. This suggests that a good input model for the time to pass through the metal detector is the exponential distribution, since its mean and standard deviation are always the same and exponential distributions are often used to model service times in queueing systems.
However, the analyst is uncomfortable with this input model because in her experience it only takes a few seconds to pass through a metal detector. She creates a histogram of the data, shown in Figure 1, which makes it immediately apparent that the time to pass through metal detection consists of two distinct distributions. Thinking carefully, she realizes that some people pass through the detector without incident, but others trigger the alarm and have to remove remaining meta
Figure 1 Histogram of 1000 observations of time through the metal detector measured in minutes.
objects and try again, in some cases even requiring a personal inspection. Therefore, three distinc input models are required for this data: one for the time to pass through without setting off the detector (the 764 left-most observations in the histogram); one for the time to pass through when the alarm does go off (the 236 right-most observations in the histogram); and a model for the chance tha a person sets off the alarm. While an exponential distribution could certainly match the summary statistics from the data (mean and standard deviation). the fitted exponential distribution would have missed a key feature of security screening, almost certainly leading to an inaccurate simulation.
Unfortunately, inspecting the data carefully the analyst spots an additional complication: The histogram in Figure 1 shows negative values in the sample (nine total). A negative time to pass through metal detection is clearly impossible, so what should the analyst do? It may be that the observations were recorded correctly but a mistake was made in calculating the times; if that is the case then the analyst may be able to reconstruct the correct values. If not, then the nine negative values should be discarded before fitting the distribution. But should they also be discarded when estimating the probability that someone sets off the alarm? That is, should the estimate be 236/1000 or 236/991? If the analyst can convince herself that the 9 negative values were actually small times that were misrecorded, then she might want to retain them for estimating this probability. If she is unsure, then the simulation should be run with both estimates to see if there is a substantial impact.
Example 3: Time-varying Data
A computer manufacturer provides a customer support center where owners of the product may cal with questions or concerns. The call center is staffed from 8A.M. to 8 P.M. Eastern Time.A simulation study is planned to help set staffing levels, since staff salaries and benefits are the primary costs. The call center has extensive records on daily call volume showing that, on average, they receive 12,277 calls per day. The number of random events in a fixed amount of time or space is often well modeled by a Poisson distributions, so a Poisson distribution is fit to the data (using methods described later in the chapter) and appears to fit well. When the number of arrivals is Poisson, then the time between arrivals—which is what we need to simulate calls—must be exponentially distributed. The natura estimate of the arrival rate for this exponential distribution is 12,277 arrivals per 12-hour day, bu since a “day” is a pretty large time unit, it is converted to 17 calls per minute.
The analysis in the previous paragraph seems to be sound, and the choice ofa Poisson distribution (implying exponential time between arrivals) was even supported by data. However, the level of data aggregation, a 12-hour day, masked a very important feature of call centers: The arrival rate of calls can, and typically does, vary substantially by time of day, day of week, and even time of the year (e.g., right after the holiday gift-giving season). We often assume that the process of interest is stationary, meaning that its basic properties do not change over time. However, if trends exist then accounting for them can be far more important than the choice of probability distribution to represent the remaining uncertainty in the system. In Section 5 we describe a method for fitting a nonstationary Poisson process, which is likely more appropriate for this call center.
Example 4: Dependent Data
Monthly demands for a particular brand of sports drink by a large retailer have been extracted from an orders database to use in a supply chain simulation. A simple input model for this data is that monthly demands are independent and identically distributed (i.i.d.), and this chapter describes methods for fitting a distribution to such data and evaluating the fit. But it is important to evaluate the “i.i.d.” assumption also.
Figure 2 Time-lagged demand data.
One informal way to check that these data are identically distributed is to plot the demands in time order to look for trends (e.g., demands are decreasing over time) or seasonality (there is a regular cycle of demand, for instance, high demand each summer followed by low demand each winter). Data with trends or seasonality should typically be “de-trended” first (usually by fitting a model to the trend or seasonal pattern) and then a distribution can be fit to any remaining variation.
Independence can be checked via time-lagged scatter plots. Figure 2 is a scatter plot of each month’s demand for the sports drink plotted against the following month’s demand (e.g., January’s demand vs. February’s demand). Clearly there is a strong negative correlation, which means large demands in one month tend to be followed by low demands in the next month, and vice versa. This feature might be the result of the retailer overstocking in one month, and then ordering less the following month so as to work off the excess inventory. Time lags greater than one month can also be examined. By blindly making the standard assumption of i.i.d. inputs this important phenomenon would be missed, leading to less effective supply chain management. In Section 7 we present methods for modeling dependent input data.
As these examples illustrate, simply having data is not enough to support effective input modeling. Data can be out of date or “dirty” (containing errors). Sometimes the effort or cost to transform data into a usable form, or “clean” it of errors, can be as significant as that required to obtain it. Inpu modeling nearly always requires the analyst to use their judgment as well as to apply appropriate statistical tools. Understanding which input models are the most and least reliable is important for judging the reliability of the conclusions drawn from the simulation study. And since uncertainty about the correctness of the input models can never be entirely eliminated, it is sensible to run the simulation with several plausible input models to see if the conclusions are robust or highly sensitive to the choices.
Many lessons can be learned from an actual experience at data collection. The first five exercises at the end of this chapter suggest some situations in which the student can gain such experience.
The following suggestions might enhance and facilitate data collection, although they are no all-inclusive.
A useful expenditure of time is in planning. This could begin by a practice or preobserving session. Try to collect data while preobserving. Devise forms for this purpose. It is very likely that these forms will have to be modified several times before the actual data collection begins. Watch for unusual circumstances and consider how they will be handled. When possible, videotape the system and extract the data later by viewing the tape. Planning is important, even if data will be collected automatically (e.g., via computer data collection), to ensure that the appropriate data are available. When data have already been collected by someone else, be sure to allow plenty of time for converting the data into a usable format.
Try to analyze the data as they are being collected. Figure out whether the data being collected are adequate to provide the distributions needed as input to the simulation. Find out whether any data being collected are useless to the simulation. There is no need to collect superfluous data.
Try to combine homogeneous data sets. Check data for homogeneity in successive time periods and during the same time period on successive days. For example, check for homogeneity of data from 2:00 P.M. to 3:00 P.M. and 3:00 P.M. to 4:00 P.M., and check to see whether the data are homogeneous for 2:00 P.M. to 3:00 P.M. on Thursday and Friday. When checking for homogeneity, an initial test is to see whether the means of the distributions (the average interarrival times, for example) are the same. The two-sample t test can be used for this purpose. A more thorough analysis would require a test of the equivalence of the distributions, perhaps via a quantile-quantile plot (described later).
Be aware of the possibility of data censoring, in which a quantity of interest is not observed in its entirety. This problem most often occurs when the analyst is interested in the time required to complete some process (for example, produce a part, treat a patient, or have a component fail), but the process begins prior to, or finishes after the completion of, the observation period. Censoring can result in especially long process times being left out of the data sample.
To discover whether there is a relationship between two variables, build a scatter diagram. Sometimes a look at the scatter diagram will indicate whether there is a relationship between the variables of interest.
Consider the possibility that a sequence of observations that appear to be independent actually has autocorrelation. Autocorrelation can exist in successive time periods or for successive customers.
Keep in mind the difference between input data and output or performance data, and be sure to collect input data. Input data typically represent the uncertain quantities that are largely beyond the control of the system and will not be altered by changes made to improve the system. Output data, on the other hand, represent the performance of the system when
subjected to the inputs, performance that we might be trying to improve. In a queueing simulation, the customer arrival times are usually inputs, whereas the customer delay is an output. Performance data are useful for model validation.
Again, these arejust a few suggestions.As a rule, data collection and analysis must be approached with great care.
2 Identifying the Distribution with Data
In this section, we discuss methods for selecting families ofinput distributions when data are available and are believed to be independent and identically distributed. The specific distribution within a family is specified by estimating its parameters, as described in Section 3. Section 6 takes up the case in which data are unavailable.
2.1 Histograms
A frequency distribution or histogram is useful in identifying the shape of a distribution. A histogram is constructed as follows:
Divide the range of the data into intervals. (Intervals are usually of equal width; however, unequal widths may be used if the heights of the frequencies are adjusted.)
Label the horizontal axis to conform to the intervals selected.
Find the frequency of occurrences within each interval.
Label the vertical axis so that the total occurrences can be plotted for each interval.
Plot the frequencies on the vertical axis.
The number of class intervals depends on the number of observations and on the amount o scatter or dispersion in the data. Hines et al. [2002] state that choosing the number of class intervals approximately equal to the square root of the sample size often works well in practice. If the intervals are too wide, the histogram will be coarse, or blocky, and its shape and other details will not show well. If the intervals are too narrow, the histogram will be ragged and will not smooth the data. Examples of ragged, coarse, and appropriate histograms of the same data are shown in Figure 3. Modern data-analysis software often allows the interval sizes to be changed easily and interactively until a good choice is found.
The histogram for continuous data corresponds to the probability density function of a theoretica distribution. If continuous, a line drawn through the center point of each class interval frequency should result in a shape like that of a pdf.
Histograms for discrete data, where there are a large number of data points, should have a cell for each value in the range of the data. However, if there are few data points, it could be necessary to combine adjacent cells to eliminate the ragged appearance of the histogram. If the histogram is associated with discrete data, it should look like a probability mass function.


Figure 3 Ragged, coarse, and appropriate histograms: (a) original data—too ragged; (b) combining adjacent cells—too coarse; (c) combining adjacent cells—appropriate.
Example 5: Discrete Data
The number of vehicles arriving at the northwest corner of an intersection in a 5-minute period between 7:00 A.M. and 7:05 A.M. was monitored for five workdays over a 20-week period. Table 1 shows the resulting data. The first entry in the table indicates that there were 125-minute periods during which zero vehicles arrived, 10 periods during which one vehicle arrived, and so on.
Table 1 Number of Arrivals in a 5-Minute Period
| Arrivals per Period | Frequency | Arrivals per Period | Frequency |
|---|---|---|---|
| 0 | 12 | 6 | 7 |
| 1 | 10 | 7 | 5 |
| 2 | 19 | 8 | 5 |
| 3 | 17 | 9 | 3 |
| 4 | 10 | 10 | 3 |
| 5 | 8 | 11 | 1 |
Figure 4 Histogram of number of arrivals per period.
The number of automobiles is a discrete variable, and there are ample data, so the histogram may have a cell for each possible value in the range of the data. The resulting histogram is shown in Figure 4.
Example 6: Continuous Data
Life tests were performed on a random sample of electronic components at 1.5 times the nomina voltage, and their lifetime (or time to failure), in days, was recorded:
| 79.919 | 3.081 | 0.062 | 1.961 | 5.845 |
|---|---|---|---|---|
| 3.027 | 6.505 | 0.021 | 0.013 | 0.123 |
| 6.769 | 59.899 | 1.192 | 34.760 | 5.009 |
| 18.387 | 0.141 | 43.565 | 24.420 | 0.433 |
| 144.695 | 2.663 | 17.967 | 0.091 | 9.003 |
| 0.941 | 0.878 | 3.371 | 2.157 | 7.579 |
| 0.624 | 5.380 | 3.148 | 7.078 | 23.960 |
| 0.590 | 1.928 | 0.300 | 0.002 | 0.543 |
| 7.004 | 31.764 | 1.005 | 1.147 | 0.219 |
| 3.217 | 14.382 | 1.008 | 2.336 | 4.562 |
Lifetime, usually considered a continuous variable, is recorded here to three-decimal-place accuracy. The histogram is prepared by placing the data in class intervals. The range of the data is rather large, from 0.002 day to 144.695 days. However, most of the values (30 of 50) are in the zero-to-5-day range. Using intervals of width three results in Table 2. The data of Table 2 are then used to prepare the histogram shown in Figure 5.
Figure 5 Histogram of component life.
2.2 Selecting the Family of Distributions
The purpose of preparing a histogram is to infer a known pdf or pmf. A family of distributions is selected on the basis of what might arise in the context being investigated along with the shape of the histogram. Thus, if interarrival-time data have been collected, and the histogram has a shape similar to an exponential distribution. Similarly, if measurements of the weights of pallets of freigh are being made, and the histogram appears symmetric about the mean, the assumption of a norma distribution would be warranted.
Table 2 Electronic Component Data
| Component Life(days) | Frequency |
|---|---|
| 23 | |
| 10 | |
| 5 | |
| 1 | |
| 1 | |
| 2 | |
| 0 | |
| 1 | |
| 1 | |
| 0 | |
| 1 | |
| 1 | |
| . | . |
| . | . |
| . | . |
| 1 | |
| . | . |
| . | . |
| . | . |
| 1 | |
| . | . |
| . | . |
| . | . |
| 1 | |
| . | . |
| . | . |
| . | . |
| 1 |
The exponential, normal, and Poisson distributions are frequently encountered and are not difficult to analyze from a computational standpoint. Although more difficult to analyze, the beta, gamma, and Weibull distributions provide a wide array of shapes and should not be overlooked during modeling of an underlying probabilistic process. Perhaps an exponential distribution was assumed, but it was found not to fit the data. The next step would be to examine where the lack of fit occurred. If the lack of fit was in one of the tails of the distribution, perhaps a gamma or Weibull distribution would fit the data more adequately.
There are literally hundreds of probability distributions that have been created; many were created with some specific physical process in mind. One aid to selecting distributions is to use the physical basis of the distributions as a guide. Here are some examples:
Binomial: Models the number of successes in n trials, when the trials are independent with common success probability p; for example, the number of defective computer chips found in a lot of n chips.
Negative Binomial (includes the geometric distribution): Models the number of trials required to achieve k successes; for example, the number of computer chips that we must inspect to find 4 defective chips.
Poisson: Models the number of independent events that occur in a fixed amount of time or space; for example, the number of customers that arrive to a store during 1 hour, or the number of defects found in 30 square meters of sheet metal.
Normal: Models the distribution of a process that can be thought of as the sum of a number of component processes; for example, a time to assemble a product that is the sum of the times required for each assembly operation. Notice that the normal distribution admits negative values, which could be impossible for process times.
Lognormal: Models the distribution of a process that can be thought of as the product of (meaning to multiply together) a number of component processes; for example, the rate of return on an investment, when interest is compounded, is the product of the returns for a number of periods.
Exponential: Models the time between independent events, or a process time that is memoryless (knowing how much time has passed gives no information about how much additional time wil pass before the process is complete); for example, the times between the arrivals from a large population of potential customers who act independently of one another. The exponential is a highly variable distribution; it is sometimes overused, because it often leads to mathematically tractable models. Recall that, if the time between events is exponentially distributed, then the number of events in a fixed period of time is Poisson.
Gamma: An extremely flexible distribution used to model nonnegative random variables. The gamma can be shifted away from 0 by adding a constant.
Beta: An extremely flexible distribution used to model bounded (fixed upper and lower limits) random variables. The beta can be shifted away from 0 by adding a constant and can be given a range larger than [0, 1] by multiplying by a constant.
Erlang: Models processes that can be viewed as the sum of several exponentially distributed processes; for example, a computer network fails when a computer and two backup computers fail, and each has a time to failure that is exponentially distributed. The Erlang is a special case of the gamma.
Weibull: Models the time to failure for components; for example, the time to failure for a disk drive. The exponential is a special case of the Weibull.
Discrete or Continuous Uniform: Models complete uncertainty: All outcomes are equally likely. This distribution often is used inappropriately when there are no data.
Triangular: Models a process for which only the minimum, most likely, and maximum values of the distribution are known; for example, the minimum, most likely, and maximum time required to test a product. This model is often a marked improvement over a uniform distribution.
Empirical: Resamples from the actual data collected; often used when no theoretical distribution seems appropriate.
Do not ignore physical characteristics of the process when selecting distributions. Is the process naturally discrete or continuous valued? Is it bounded or is there no natural bound? This knowledge, which does not depend on data, can help narrow the family of distributions from which to choose. And keep in mind that there is no “true” distribution for any stochastic input process. An input mode is an approximation of reality, so the goal is to obtain an approximation that yields useful results from the simulation experiment.
The reader is encouraged to complete Exercises 6 through 11 to learn more about the shapes of the distributions mentioned in this section. Examining the variations in shape as the parameters change is very instructive.
2.3 Quantile-Quantile Plots
The construction of histograms, as discussed in Section 2.1, and the recognition of a distributiona shape, as discussed in Section 2.2, are necessary ingredients for selecting a family of distributions to represent a sample of data. However, a histogram is not as useful for evaluating the of the chosen distribution. When there is a small number of data points, say, 30 or fewer, a histogram can be rather ragged. Further, our perception of the fit depends on the widths of the histogram intervals. But, even if the intervals are well chosen, grouping data into cells makes it difficult to compare a histogram to a continuous probability density function. A quantile-quantile plot is a useful tool for evaluating distribution fit, one that does not suffer from these problems.
If X is a random variable with cdf F, then the q-quantile of X is that value such that , for . When F has an inverse, we write Now let be a sample of data from X. Order the observations from the smallest to the largest, and denote these as , where . Let j denote the ranking or order number. Therefore, for the smallest and for the largest. The plot is based on the fact that is an estimate of the quantile of X. In other words,
Now, suppose that we have chosen a distribution with cdf as a possible representation of the distribution of X. If is a member of an appropriate family of distributions, then a plot of versus ) will be approximately a straight line. If F is from an appropriate family of distributions and also has appropriate parameter values, then the line will have slope 1. On the other hand, if the assumed distribution is inappropriate, the points will deviate from a straight line,
usually in a systematic manner. The decision about whether to reject some hypothesized model is subjective.
Example 7: Normal Q-Q Plot
A robot is used to install the doors on automobiles along an assembly line. It was thought that the installation times followed a normal distribution. The robot is capable of measuring installation times accurately. A sample of 20 installation times was automatically taken by the robot, with the following results, where the values are in seconds:
| 99.79 | 99.56 | 100.17 | 100.33 |
|---|---|---|---|
| 100.26 | 100.41 | 99.98 | 99.83 |
| 100.23 | 100.27 | 100.02 | 100.47 |
| 99.55 | 99.62 | 99.65 | 99.82 |
| 99.96 | 99.90 | 100.06 | 99.85 |
The sample mean is 99.99 seconds, and the sample variance is (0.2832)^2 seconds^2. These values can serve as the parameter estimates for the mean and variance of the normal distribution. The observations are now ordered from smallest to largest as follows:
| j | Value | j | Value | j | Value | j | Value |
|---|---|---|---|---|---|---|---|
| 1 | 99.55 | 6 | 99.82 | 11 | 99.98 | 16 | 100.26 |
| 2 | 99.56 | 7 | 99.83 | 12 | 100.02 | 17 | 100.27 |
| 3 | 99.62 | 8 | 99.85 | 13 | 100.06 | 18 | 100.33 |
| 4 | 99.65 | 9 | 99.90 | 14 | 100.17 | 19 | 100.41 |
| 5 | 99.79 | 10 | 99.96 | 15 | 100.23 | 20 | 100.47 |
The ordered observations are then plotted versus , for , where F is the cdf of the normal distribution with mean 99.99 and variance (0.2832)^2, to obtain a q-q plot. The plotted values are shown in Figure 6, along with a histogram of the data. Notice that it is difficul to tell whether the data are well represented by a normal distribution from looking at the histogram, but the general perception of a straight line is quite clear in the q-q plot and supports the hypothesis of a normal distribution.
In the evaluation of the linearity of a q-q plot, the following should be considered:
a. The observed values will never fall exactly on a straight line.
b. The ordered values are not independent; they have been ranked. Hence, if one point is above a straight line, it is likely that the next point will also lie above the line. And it is unlikely that the points will be evenly scattered about the line.
c. The variances of the extremes (largest and smallest values) are much higher than the variances in the middle of the plot. Greater discrepancies can be accepted at the extremes. The linearity of the points in the middle of the plot is more important than the linearity at the extremes.

Figure 6 A q-q plot and histogram of the installation times.
Modern data-analysis software often includes tools for generating q-q plots, especially for the normal distribution. The plot can also be used to compare two samples of data to see whether they can be represented by the same distribution (that is, that they are homogeneous). are a sample of the random variable , and are a sample of the random variable then plotting the ordered values of X versus the ordered values of Z will reveal approximately a straigh line if both samples are well represented by the same distribution (Chambers, Cleveland, and Tukey [1983]).
3 Parameter Estimation
After a family of distributions has been selected, the next step is to estimate the parameters o the distribution. Estimators for many useful distributions are described in this section. In addition, many software packages—some of them integrated into simulation languages—are now available to compute these estimates.
3.1 Preliminary Statistics: Sample Mean and Sample Variance
In a number of instances, the sample mean, or the sample mean and sample variance, are used to estimate the parameters of a hypothesized distribution; see Example 7. In the following paragraphs, three sets of equations are given for computing the sample mean and sample variance. Equations (1) and (2) can be used when discrete or continuous raw data are available. Equations (3) and (4) are used when the data are discrete and have been grouped in a frequency distribution. Equations (5) and (6) are used when the data are discrete or continuous and have been placed in class intervals. Equations (5) and (6) are approximations and should be used only when the raw data are unavailable.
If the observations in a sample of size n are , the sample mean is defined by
and the sample variance is defined by
If the data are discrete and have been grouped in a frequency distribution, Equations (1) and (2) can be modified to provide for much greater computational efficiency. The sample mean can be computed as
and the sample variance as
where k is the number of distinct values of X and is the observed frequency of the value of X.
Example 8: Grouped Data
The data in Table 1 can be analyzed to obtain , and . From Equation (3),
and, from Equation (4),
The sample standard deviation S is just the square root of the sample variance. In this case,. Equations (1) and (2) would have yielded exactly the same results for and It is preferable to use the raw data, if possible, when the values are continuous. However, data sometimes are received after having been placed in class intervals. Then it is no longer possible to obtain the exact sample mean and variance. In such cases, the sample mean and sample variance are approximated from the following equations:
and
where is the observed frequency in the jth class interval, is the midpoint of the jth interval, and c is the number of class intervals.
Example 9: Continuous Data in Class Intervals
Assume that the raw data on component life shown in Example 6 either was discarded or was lost. However, the data shown in Table 2 are still available. To approximate values for X¯ and , Equations (5) and (6) are used. The following values are created: and . With , X is approximated from Equation (5) as
Then, is approximated from Equation (6) as
and
Applying Equations (1) and (2) to the original data in Example 6 results in and . Thus, when the raw data are either discarded or lost, inaccuracies could result
Table 3 Suggested Estimators for Distributions Often Used in Simulation
| Distribution | Parameter(s) | Suggested Estimator(s) |
|---|---|---|
| Poisson | ||
| Exponential | ||
| Gamma | (see Table A.9) | |
| Normal | (unbiased) | |
| Lognormal | (after taking ln of the data) (after taking ln of the data) | |
| Weibullwith | See Equations (11) and (14)for and Iterate until convergence | |
| Beta | where is the digamma function, and |
3.2 Suggested Estimators
Numerical estimates of the distribution parameters are needed to reduce the family of distributions to a specific distribution and to test the resulting hypothesis. Table 3 contains suggested estimators for distributions often used in simulation. Except for an adjustment to remove bias in the estimate of for the normal distribution, these estimators are the maximum-likelihood estimators based on the raw data. (If the data are in class intervals, these estimators must be modified.) The reader is referred to Fishman [1973] and Law [2007] for parameter estimates for the uniform, binomial, and negative binomial distributions. The triangular distribution is usually employed when no data are available, with the parameters obtained from educated guesses for the minimum, most likely, and maximum possible values; the uniform distribution may also be used in this way if only minimum and maximum values are available.
Examples of the use of the estimators are given in the following paragraphs. The reader should keep in mind that a parameter is an unknown constant, but the estimator is a statistic (or random variable), because it depends on the sample values. To distinguish the two clearly here, if, say, a parameter is denoted by α, the estimator will be denoted by α.
Example 10: Exponential Distribution
We will use the exponential distribution to illustrate the maximum likelihood method for obtaining parameter estimators. The density function of the exponential distribution with rate parameter λ is
for . If are i.i.d., and each have this exponential distribution, then their join distribution is
The joint distribution represents, roughly, the likelihood of any collection of values.
The maximum likelihood method turns this around in the sense that, if we have a sample of data, say , but λ is not known, then the maximum-likelihood estimator (MLE) is the value of that maximizes the likelihood of the sample, as measured by Equation (7). Thus, the MLE of λ for the exponential distribution maximizes the likelihood function
Finding the MLE is often a calculus exercise of maximizing the likelihood function with respect to the unknown parameters. Because the likelihood function is a product of density functions and it is positive, it is sometimes easier to maximize the log of the likelihood function, which in this case is
Taking the derivative with respect to and setting it equal to we get
giving the MLE where is the sample mean of the observations.
For example, assuming that the data in Example 6 come from an exponential distribution, the MLE of λ is obtained from as
Suppose that a random sample of size n , has been taken and that the observations are assumed to come from a Weibull distribution. The likelihood function can be shown to be
The maximum-likelihood estimates are those values of and that maximize or, equivalently, maximize ln , denoted by . The maximum value of is obtained by taking the partial derivatives and , setting each to zero, and solving the resulting equations, which, after substitution, become
and
where
The maximum-likelihood estimates, and , are the solutions of Equations (9) and (10). First,is found via the iterative procedure explained below. Then is found from Equation (10), with Equation (9) is nonlinear, so it is necessary to use a numerical-analysis technique to solve it. In Table , a suggested iterative method for computing is given as
Equation (12) employs Newton’s method in reaching where is thejth iteration, beginning with an initial estimate for , given in Table 3, as follows:
If the initial estimate,, is sufficiently close to the solution , then approaches In Newton’s method, is approached through increments of size . Equation (11) is used to compute and Equation (14) is used to compute , as follows:
Equation (14) can be derived from Equation (11) by differentiating with respect to . The iterative process continues until , that is, unti $| f ( \widehat {\beta} _ {j} ) | \leq 0 . 001 $ Consider the data given in Example 6. These data concern the failure of electronic components and look to come from an exponential distribution. In Example 10, the parameter was estimated on the hypothesis that the data were from an exponential distribution. If this hypothesis is rejected, an alternative hypothesis is that the data come from a Weibull distribution. The Weibull distribution is suspected because the data pertain to electronic component failures, which occur suddenly.
Equation (13) is used to compute . For the data in Example , and ; so is found by Equation (2) to be
and . Thus,
To compute by using Equation (12) requires the calculation of from Equations (11) and (14). The following additional values are needed:, and . Thus,
and
Then, by Equation (12),
After four iterations,$| f ( \widehat {\beta} _ {3} ) | \le 0 . 001 $, at which point , is the approximate solution to Equation (9). Table 4 contains the values needed to complete each iteration.
Now, can be computed from Equation (10) with , as follows:
Table 4 Iterative Estimation of Parameters of the Weibull Distribution
| j | |||||||
|---|---|---|---|---|---|---|---|
| 0 | 0.477 | 115.125 | 292.629 | 1057.781 | 16.024 | -356.110 | 0.522 |
| 1 | 0.522 | 129.489 | 344.713 | 1254.111 | 1.008 | -313.540 | 0.525 |
| 2 | 0.525 | 130.603 | 348.769 | 1269.547 | 0.004 | -310.853 | 0.525 |
| 3 | 0.525 | 130.608 | 348.786 | 1269.614 | 0.000 | -310.841 | 0.525 |
If is sufficiently close to the procedure converges quickly, usually in four to five iterations. However, if the procedure appears to be diverging, try other initial guesses for for example, one-half the initial estimate or twice the initial estimate.
The difficult task of estimating parameters for the Weibull distribution by hand emphasizes the value of having software support for input modeling.
Example 12: Poisson Distribution
Assume that the arrival data in Table 1 require analysis. An examination of Figure 4 suggests a Poisson distribution assumption with unknown parameter α. From Table 3, the estimator of α is which was found in Example 8. Thus,. Recall that the true mean and variance are equal for the Poisson distribution. In Example 8, the sample variance was estimated as . However, it should never be expected that the sample mean and the sample variance will be precisely equal, because each is a random variable.
Example 13: Lognormal Distribution
The rates of return on 10 investments in a portfolio are 18.8, 27.9, 21.0, 6.1, 37.4, 5.0, 22.9, 1.0, 3.1, and 8.3 percent. To estimate the parameters of a lognormal model of these data, we first take the natural log of the data and obtain 2.9, 3.3, 3.0, 1.8, 3.6, 1.6, 3.1, 0, 1.1, and 2.1. Then we set and
Example 14: Normal Distribution
The parameters of the normal distribution, and , are estimated by X¯ and , as shown in Table 3. The plot in Example 7 leads to a distributional assumption that the installation times are normal. From Equations (1) and (2), the data in Example 7 yield and seconds^2.
Example 15: Gamma Distribution
The estimator for the gamma distribution is chosen by referring to Table A.9. Table A.9 requires the computation of the quantity , where
Also, it can be seen in Table 3 that is given by
Lead time is often gamma-distributed. Suppose that the lead times (in days) associated with 20 orders have been accurately measured as follows:
| Order | Lead Time (days) | Order | Lead Time (days) |
|---|---|---|---|
| 1 | 70.292 | 11 | 30.215 |
| 2 | 10.107 | 12 | 17.137 |
| 3 | 48.386 | 13 | 44.024 |
| 4 | 20.480 | 14 | 10.552 |
| 5 | 13.053 | 15 | 37.298 |
| 6 | 25.292 | 16 | 16.314 |
| 7 | 14.713 | 17 | 28.073 |
| 8 | 39.166 | 18 | 39.019 |
| 9 | 17.421 | 19 | 32.330 |
| 10 | 13.905 | 20 | 36.547 |
To estimate and it is first necessary to compute M from Equation (15). Here, is found, from Equation (1), to be
Then
Next
Then
and
By interpolation in Table A.9 in the Appendix,. Finally, Equation (16) results in
Example 16: Beta Distribution
The percentage of customers each month who bring in store coupons must be between 0 and 100 percent. Observations at a store for eight months gave the values 25%, 74%, 20%, 32%, 81%, 47%, 31%, and 8%. To fit a beta distribution to these data, we first need to rescale it to the interval [0, 1] by dividing all the values by 100, which yields 0.25, 0.74, 0.20, 0.32, 0.81, 0.47, 0.31, 0.08.
The maximum-likelihood estimators of the parameters solve the system of equations shown in Table 9.3. Such equations can be solved by modern symbolic/numerical calculation programs, such as Maple; a Maple procedure for the beta parameters is shown in Figure 7. In this case, the solutions are and ```txt betaMLE := proc(X, n) local G1, G2, beta1, beta2, eqns, solns; G1 := product(X[i], i=1..n)^(1/n); G2 := product(1-X[i], i=1..n)^(1/n); eqns := {Psi(beta1) - Psi(beta1 + beta2) = ln(G1), Psi(beta2) - Psi(beta1 + beta2) = ln(G2)}; solns := fsolve(eqns, {beta1=0..infinity, beta2=0..infinity}); RETURN(solns); end;
Unfortunately, in some situations, a simulation study must be undertaken when there is not time or resources to collect data on which to base input models. When this happens, the analyst must use any available information—such as manufacturer specifications and expert opinion—to construct the input models. When input models are derived without the benefit of data, it is particularly importan to examine the sensitivity of the results to the models chosen.
Many, but not all, input processes can be represented as sequences of independent and identically distributed random variables. When inputs should exhibit dependence, then multivariate-input models are required. The bivariate normal distribution (and more generally the multivariate normal distribution) is often used to represent a finite number of dependent random variables. Time-series models are useful for representing a (conceptually infinite) sequence of dependent inputs. The NORTA transformation facilitates developing multivariate-input models with marginal distributions that are no normal.
REFERENCES
BILLER, B., AND B. L. NELSON [2003], “Modeling and Generating Multivariate Time Series with Arbitrary Marginals Using an Autoregressive Technique,” ACM Transactions on Modeling and Computer Simulation, Vol. 13, pp. 211–237.
BRATLEY, P., B. L. FOX, AND L. E. SCHRAGE [1987], A Guide to Simulation, 2d ed., Springer-Verlag, New York.
CARIO, M. C., AND B. L. NELSON [1996], “Autoregressive to Anything: Time-Series Input Processes for Simulation,” Operations Research Letters, Vol. 19, pp. 51–58.
CARIO, M. C., AND B. L. NELSON [1998], “Numerical Methods for Fitting and Simulating Autoregressiveto-Anything Processes,” INFORMS Journal on Computing, Vol. 10, pp. 72–81.
CHOI, S. C., AND R. WETTE [1969], “Maximum Likelihood Estimation of the Parameters of the Gamma Distribution and Their Bias,” Technometrics, Vol. 11, No. 4, pp. 683–890.
CHAMBERS, J. M., W. S. CLEVELAND, AND P. A. TUKEY [1983], Graphical Methodsfor Data Analysis, CRC Press, Boca Raton, FL.
CONNOVER, W. J. [1998], Practical Nonparametric Statistics, 3d ed., Wiley, New York.
DURBIN, J. [1975], “Kolmogorov–Smirnov Tests When Parameters Are Estimated with Applications to Tests of Exponentiality and Tests on Spacings,” Biometrika, Vol. 65, pp. 5–22.
FISHMAN, G. S. [1973], Concepts and Methods in Discrete Event Digital Simulation, Wiley, New York.
GUMBEL, E. J. [1943], “On the Reliability ofthe Classical Chi-squared Test,”Annals ofMathematical Statistics, Vol. 14, pp. 253ff.
HINES, W. W., D. C. MONTGOMERY, D. M. GOLDSMAN, AND C. M. BORROR [2002], Probability and Statistics in Engineering and Management Science, 4th ed., Wiley, New York.
JOHNSON, M. A., S. LEE, AND J. R. WILSON [1994], “NPPMLE and NPPSIM: Software for Estimating and Simulating Nonhomogeneous Poisson Processes Having Cyclic Behavior,” Operations Research Letters, Vol. 15, pp. 273–282.
JOHNSON, M. E. [1987], Multivariate Statistical Simulation, Wiley, New York.
LAW, A. M. [2007], Simulation Modeling and Analysis, 4th ed., McGraw-Hill, New York.
LILLIEFORS, H. W. [1967], “On the Kolmogorov–Smirnov Test for Normality with Mean and Variance Unknown,” Journal ofthe American Statistical Association, Vol. 62, pp. 339–402.
LILLIEFORS, H. W. [1969], “On the Kolmogorov–Smirnov Test for the Exponential Distribution with Mean Unknown,” Journal ofthe American Statistical Association, Vol. 64, pp. 387–389.
MANN, H. B., AND A. WALD [1942], “On the Choice of the Number of Intervals in the Application of the Chi-squared Test,” Annals ofMathematical Statistics, Vol. 18, p. 50ff.
NELSON, B. L.,AND M.YAMNITSKY [1998], “Input Modeling Tools for Complex Problems,” in Proceedings of the 1998 Winter Simulation Conference, D. Medeiros, E. Watson, J. Carson, and M. Manivannan, eds., Washington, DC, Dec. 13–16, pp. 105–112.
STUART, A., J. K. ORD, AND E. ARNOLD [1998], Kendall’s Advanced Theory of Statistics, 6th ed., Vol. 2, Oxford University Press, Oxford
EXERCISES
Go to a small store and record the interarrival- and service-time distributions. If there are severa workers, how do the service-time distributions compare to one another? Do service-time distributions need to be constructed for each type of appliance? (Make sure that the management gives permission to perform this study.)
Go to a cafeteria and collect data on the distributions of interarrival and service times. The distribution of interarrival times is probably different for each of the three daily meals and migh also vary during the meal—that is, the interarrival time distribution for 11:00 A.M. to 12:00 noon could be different from that for 12:00 noon to 1:00 P.M. Define service time as the time from when the customer reaches the point at which the first selection could be made until the time of exiting from the cafeteria line. (Any reasonable modification of this definition is acceptable.) The service-time distribution probably changes for each meal. Can times of the day or days of the week for either distribution be grouped to suit the homogeneity of the data? (Make sure tha the management gives permission to perform this study.)
Go to a major traffic intersection and record the interarrival-time distributions from each direction. Some arrivals want to go straight, some turn left, some turn right. The interarrival-time distribution varies during the day and by day of the week. Every now and then an acciden occurs. Develop an input model for your data.
Go to a grocery store and construct the interarrival and service distributions at the checkout counters. These distributions might vary by time of day and by day of week. Also record the number of service channels available at all times. (Make sure that the management gives permission to perform this study.)
Go to a laundromat and collect data to develop input models for the number of washers and dryers a customer uses (probably dependent). Also collect data on the arrival rate of customers (probably not stationary). (Make sure that the management gives permission to perform this study.)
Prepare four theoretical normal density functions, all on the same figure, each distribution having mean zero, but let the standard deviations be 1/4, 1/2, 1, and 2.
On one figure, draw the pdfs of the Erlang distribution where and , and 8.
On one figure, draw the pdfs of the Erlang distribution where θ 2 and k 1, 2, 4, and 8.
Draw the pmf of the Poisson distribution that results when the parameter α is equal to the following:
On one figure, draw the two exponential pdfs that result when the parameter λ equals 0.6 and 1.2.
On one figure, draw the three Weibull pdfs that result when ν 0,, and , and 4.
The following data are generated randomly from a gamma distribution:
| 1.691 | 1.437 | 8.221 | 5.976 |
|---|---|---|---|
| 1.116 | 4.435 | 2.345 | 1.782 |
| 3.810 | 4.589 | 5.313 | 10.90 |
| 2.649 | 2.432 | 1.581 | 2.432 |
| 1.843 | 2.466 | 2.833 | 2.361 |
Compute the maximum-likelihood estimators and 13. The following data are generated randomly from a Weibull distribution where | 7.936 | 5.224 | 3.937 | 6.513 | | — | — | — | — | | 4.599 | 7.563 | 7.172 | 5.132 | | 5.259 | 2.759 | 4.278 | 2.696 | | 6.212 | 2.407 | 1.857 | 5.002 | | 4.612 | 2.003 | 6.908 | 3.326 |
Compute the maximum-likelihood estimators α and (This exercise requires a programmable calculator, a computer, or a lot of patience.)
- The highway between Atlanta, Georgia and Athens, Georgia has a high incidence of accidents along its 100 kilometers. Public safety officers say that the occurrence of accidents along the
highway is randomly (uniformly) distributed, but the news media say otherwise. The Georgia Department of Public Safety published records for the month of September. These records indicated the point at which 30 accidents involving an injury or death occurred, as follows (the data points representing the distance from the city limits of Atlanta):
| 88.3 | 40.7 | 36.3 | 27.3 | 36.8 |
|---|---|---|---|---|
| 91.7 | 67.3 | 7.0 | 45.2 | 23.3 |
| 98.8 | 90.1 | 17.2 | 23.7 | 97.4 |
| 32.4 | 87.8 | 69.8 | 62.6 | 99.7 |
| 20.6 | 73.1 | 21.6 | 6.0 | 45.3 |
| 76.6 | 73.2 | 27.3 | 87.6 | 87.2 |
Use the Kolmogorov–Smirnov test to discover whether the distribution of location of accidents is uniformly distributed for the month of September.
- Show that the Kolmogorov–Smirnov test statistic for Example 19 is 16. Records pertaining to the monthly number of job-related injuries at an underground coal mine were being studied by a federal agency. The values for the past 100 months were as follows:
| Injuries per Month | Frequency of Occurrence |
|---|---|
| 0 | 35 |
| 1 | 40 |
| 2 | 13 |
| 3 | 6 |
| 4 | 4 |
| 5 | 1 |
| 6 | 1 |
(a) Apply the chi-square test to these data to test the hypothesis that the underlying distribution is Poisson. Use the level of significance (b) Apply the chi-square test to these data to test the hypothesis that the distribution is Poisson with mean 1.0. Again let (c) What are the differences between parts (a) and (b), and when might each case arise?
- The time required for 50 different employees to compute and record the number of hours worked during the week was measured, with the following results in minutes:
| Employee | Time (minutes) | Employee | Time (minutes) |
|---|---|---|---|
| 1 | 1.88 | 26 | 0.04 |
| 2 | 0.54 | 27 | 1.49 |
| 3 | 1.90 | 28 | 0.66 |
| 4 | 0.15 | 29 | 2.03 |
| 5 | 0.02 | 30 | 1.00 |
| 6 | 2.81 | 31 | 0.39 |
| 7 | 1.50 | 32 | 0.34 |
| 8 | 0.53 | 33 | 0.01 |
| 9 | 2.62 | 34 | 0.10 |
| 10 | 2.67 | 35 | 1.10 |
| 11 | 3.53 | 36 | 0.24 |
| 12 | 0.53 | 37 | 0.26 |
| 13 | 1.80 | 38 | 0.45 |
| 14 | 0.79 | 39 | 0.17 |
| 15 | 0.21 | 40 | 4.29 |
| 16 | 0.80 | 41 | 0.80 |
| 17 | 0.26 | 42 | 5.50 |
| 18 | 0.63 | 43 | 4.91 |
| 19 | 0.36 | 44 | 0.35 |
| 20 | 2.03 | 45 | 0.36 |
| 21 | 1.42 | 46 | 0.90 |
| 22 | 1.28 | 47 | 1.03 |
| 23 | 0.82 | 48 | 1.73 |
| 24 | 2.16 | 49 | 0.38 |
| 25 | 0.05 | 50 | 0.48 |
Use the chi-square test (as in Example 18) to test the hypothesis that these service times are exponentially distributed. Let the number of class intervals be k 6. Use the level of significance α 0.05.
| 218.95 | 232.75 | 212.80 | 231.10 | 215.95 |
|---|---|---|---|---|
| 237.55 | 235.45 | 228.25 | 218.65 | 212.80 |
| 230.35 | 228.55 | 216.10 | 229.75 | 229.00 |
| 199.75 | 225.10 | 208.15 | 213.85 | 205.45 |
| 219.40 | 208.15 | 198.40 | 238.60 | 219.55 |
| 243.10 | 198.85 | 224.95 | 212.20 | 222.90 |
| 218.80 | 203.35 | 223.45 | 213.40 | 206.05 |
| 229.30 | 239.20 | 201.25 | 216.85 | 207.25 |
| 204.85 | 219.85 | 226.15 | 230.35 | 211.45 |
| 227.95 | 229.30 | 225.25 | 201.25 | 216.10 |
Using input-modeling software, apply as many tests for normality as are available in the software. If the chi-square test is available, apply it with at least two different choices for the number of intervals. Do all of the tests reach the same conclusion?
- The Crosstowner was a bus that cut a diagonal path from northeast Atlanta to southwest Atlanta. The time required to complete the route was recorded by the bus operator. The bus runs from Monday through Friday. The times of the last fifty 8:00 A.M. runs, in minutes, are as follows:
| 92.3 | 92.8 | 106.8 | 108.9 | 106.6 |
|---|---|---|---|---|
| 115.2 | 94.8 | 106.4 | 110.0 | 90.9 |
| 104.6 | 72.0 | 86.0 | 102.4 | 99.8 |
| 87.5 | 111.4 | 105.9 | 90.7 | 99.2 |
| 97.8 | 88.3 | 97.5 | 97.4 | 93.7 |
| 99.7 | 122.7 | 100.2 | 106.5 | 105.5 |
| 80.7 | 107.9 | 103.2 | 116.4 | 101.7 |
| 84.8 | 101.9 | 99.1 | 102.2 | 102.5 |
| 111.7 | 101.5 | 95.1 | 92.8 | 88.5 |
| 74.4 | 98.9 | 111.9 | 96.5 | 95.9 |
How are these run times distributed? Develop and test a suitable model.
- The time required for the transmission of a message (in milliseconds) is sampled electronically at a communications center. The last 50 values in the sample are as follows:
| 7.936 | 4.612 | 2.407 | 4.278 | 5.132 |
|---|---|---|---|---|
| 4.599 | 5.224 | 2.003 | 1.857 | 2.696 |
| 5.259 | 7.563 | 3.937 | 6.908 | 5.002 |
| 6.212 | 2.759 | 7.172 | 6.513 | 3.326 |
| 8.761 | 4.502 | 6.188 | 2.566 | 5.515 |
| 3.785 | 3.742 | 4.682 | 4.346 | 5.359 |
| 3.535 | 5.061 | 4.629 | 5.298 | 6.492 |
| 3.502 | 4.266 | 3.129 | 1.298 | 3.454 |
| 5.289 | 6.805 | 3.827 | 3.912 | 2.969 |
| 4.646 | 5.963 | 3.829 | 4.404 | 4.924 |
How are the transmission times distributed? Develop and test an appropriate model.
- The time (in minutes) between requests for the hookup ofelectric service was accurately recorded at the Gotwatts Flash and Flicker Company, with the following results for the last 50 requests:
| 0.661 | 4.910 | 8.989 | 12.801 | 20.249 |
|---|---|---|---|---|
| 5.124 | 15.033 | 58.091 | 1.543 | 3.624 |
| 13.509 | 5.745 | 0.651 | 0.965 | 62.146 |
| 15.512 | 2.758 | 17.602 | 6.675 | 11.209 |
| 2.731 | 6.892 | 16.713 | 5.692 | 6.636 |
| 2.420 | 2.984 | 10.613 | 3.827 | 10.244 |
| 6.255 | 27.969 | 12.107 | 4.636 | 7.093 |
| 6.892 | 13.243 | 12.711 | 3.411 | 7.897 |
| 12.413 | 2.169 | 0.921 | 1.900 | 0.315 |
| 4.370 | 0.377 | 9.063 | 1.875 | 0.790 |
How are the times between requests for service distributed? Develop and test a suitable model.
- Daily demands for transmission overhaul kits for the D-3 dragline were maintained by Earth Moving Tractor Company, with the following results:
| 0 | 2 | 0 | 0 | 0 |
|---|---|---|---|---|
| 1 | 0 | 1 | 1 | 1 |
| 0 | 1 | 0 | 0 | 0 |
| 2 | 0 | 1 | 0 | 1 |
| 0 | 1 | 0 | 0 | 2 |
| 1 | 0 | 1 | 0 | 0 |
| 0 | 0 | 0 | 0 | 0 |
| 1 | 0 | 1 | 0 | 1 |
| 0 | 0 | 3 | 0 | 1 |
| 1 | 0 | 0 | 0 | 0 |
How are the daily demands distributed? Develop and test an appropriate model.
- A simulation is to be conducted of a job shop that performs two operations: milling and planing, in that order. It would be possible to collect data about processing times for each operation, then generate random occurrences from each distribution. However, the shop manager says that the times might be related; large milling jobs take lots of planing. Data are collected for the next 25 orders, with the following results in minutes:
| Order | Milling Time (minutes) | Planing Time (minutes) | Order | Milling Time (minutes) | Planing Time (minutes) |
|---|---|---|---|---|---|
| 1 | 12.3 | 10.6 | 14 | 24.6 | 16.6 |
| 2 | 20.4 | 13.9 | 15 | 28.5 | 21.2 |
| 3 | 18.9 | 14.1 | 16 | 11.3 | 9.9 |
| 4 | 16.5 | 10.1 | 17 | 13.3 | 10.7 |
| 5 | 8.3 | 8.4 | 18 | 21.0 | 14.0 |
| 6 | 6.5 | 8.1 | 19 | 19.5 | 13.0 |
| 7 | 25.2 | 16.9 | 20 | 15.0 | 11.5 |
| 8 | 17.7 | 13.7 | 21 | 12.6 | 9.9 |
| 9 | 10.6 | 10.2 | 22 | 14.3 | 13.2 |
| 10 | 13.7 | 12.1 | 23 | 17.0 | 12.5 |
| 11 | 26.2 | 16.0 | 24 | 21.2 | 14.2 |
| 12 | 30.4 | 18.9 | 25 | 28.4 | 19.1 |
| 13 | 9.9 | 7.7 |
(a) Plot milling time on the horizontal axis and planing time on the vertical axis. Do these data seem dependent? (b) Compute the sample correlation between milling time and planing time. (c) Fit a bivariate normal distribution to these data.
Write a computer program to compute the maximum-likelihood estimators of the Weibull distribution. Inputs to the program should include the sample size the observations a stopping criterion (stop when $| f ( \widehat {\beta} _ {j} ) | \leq \epsilon ) $; and a print option OPT (usually set = 0). Output would be the estimates α and , additional output would be printed, as in Table 4, showing convergence. Make the program as “user friendly” as possible.
Examine a computer-software library or simulation-support environment to which you have access. Obtain documentation on data-analysis software that would be useful in solving exercises 7 through 24. Use the software as an aid in solving selected problems.
The numbers of patrons staying at a small hotel on 20 successive nights was observed to be 20, 14, 21, 19, 14, 18, 21, 25, 27, 26, 22, 18, 13, 18, 18, 18, 25, 23, 20, 21. Fit both an AR(1) and an EAR(1) model to these data. Decide which model provides a better fit by looking at a histogram of the data.
The following data represent the time to perform transactions in a bank, measured in minutes: 0.740, 1.28, 1.46, 2.36, 0.354, 0.750, 0.912, 4.44, 0.114, 3.08, 3.24, 1.10, 1.59, 1.47, 1.17, 1.27, 9.12, 11.5, 2.42, 1.77. Develop an input model for these data.
Two types ofjobs (A and B) are released to the input buffer of a job shop as orders arrive, and the arrival of orders is uncertain. The following data are available from the last week of production:
| Day | Number of Jobs | Number of As |
|---|---|---|
| 1 | 83 | 53 |
| 2 | 93 | 62 |
| 3 | 112 | 66 |
| 4 | 65 | 41 |
| 5 | 78 | 55 |
Develop an input model for the number of new arrivals of each type each day.
The following data are available on the processing time at a machine (in minutes): 0.64, 0.59, 1.1, 3.3, 0.54, 0.04, 0.45, 0.25, 4.4, 2.7, 2.4, 1.1, 3.6, 0.61, 0.20, 1.0, 0.27, 1.7, 0.04, 0.34. Develop an input model for the processing time.
For the arrival-count data shown here, estimate the arrival-rate function λ(t) for an NSPP in arrivals per hour:
| Time Period | Number of Arrivals | |||
|---|---|---|---|---|
| Day 1 | Day 2 | Day 3 | Day 4 | |
| 8:00–10:00 | 22 | 24 | 20 | 28 |
| 10:00–12:00 | 23 | 26 | 32 | 30 |
| 12:00–2:00 | 40 | 33 | 32 | 38 |
Using the web, research some of the input-modeling software packages mentioned in this chapter (try www.informs-sim.org as a starting place). What are their features? What distributions do they include?
As part of a surgical admitting process orderlies are available to escort patients to the presurgery preparation area. Patients are not allowed to go by themselves as a matter of policy. A Management Engineer walked the route briskly and found it took 2 minutes to walk to the prep area. Orderlies say that it sometimes takes as long as 7 minutes to escort a patient to the area, but it usually takes 5 minutes. Construct an input model for time to escort a patient based on the information given.
At an insertion/sealing/inspection operation electronic components are inserted into a board, the case is assembled and sealed, and the completed unit is tested. The time to accomplish all of this is expected to be 2 minutes for type A12117c assemblies and 3 minutes for the B33433x assemblies. An average deviation of plus-or-minus 20% around these values is considered the standard allowance for variability. Construct an input model for the insertion/sealing/inspection operation based on the information given.
The following data are counts of calls arriving to a call center by hour of the day over five Mondays. Does it appear that the process is nonstationary? If so, then develop an NSPP inpu model for the arrival of calls between 8 A.M. and 4 P.M.
| 8-9A.M. | 9-10A.M. | 10-11A.M. | 11-12P.M. | 12-1P.M. | 1-2P.M. | 2-3P.M. | 3-4P.M. |
|---|---|---|---|---|---|---|---|
| 27 | 37 | 58 | 68 | 65 | 33 | 37 | 21 |
| 27 | 35 | 67 | 93 | 74 | 42 | 39 | 21 |
| 25 | 39 | 58 | 75 | 82 | 34 | 46 | 19 |
| 18 | 42 | 48 | 75 | 62 | 51 | 49 | 14 |
| 29 | 42 | 65 | 88 | 70 | 43 | 45 | 22 |